MSTelcom Complexo TCC2

The design contemplated the implantation of the complex buildings, infrastructure and supply depots for their diesel generators, corresponding earthworks and construction of an underground technical gallery that will serve the entire complex where they are installed and all networks, hydraulic, electrical and telecommunication in closed ring. To highlight the ecological point of view of the design, that predicted the use of stormwater through ponds reusing water for irrigation and water supply for the entire complex.

client
MSTelcom

location
Zango, Angola

project
2011

intervention area
14 000 m2

Earthworks

66 500m3 excavation
47 300 m3 fill
soapro estudos e projectos
hydraulic eng.
transport. inf.
electrical eng.
mechanical eng.