The rehabilitation of the area surrounding the headquarters of the MPLA in Cabinda extends over a total length of about 800 m, connecting the end of the Forças Armadas street to the Dr. Agostinho Neto street, passing the Identification and Criminal Register Building and the Cabinda Provincial Hospital.

The rehabilitation includes the urban landscaping of streets, with the delineation of carriageways and pavements, as well as the creation of new plumbing infrastructure, such as the water supply network, the stormwater drainage network and the domestic sewage network and new electrical and telecommunications infrastructures.

client
Governo da Província de Cabinda

local
Cabinda, Angola

projecto
2010

extensão total
800m

velocidade de projecto
60 km/h

tipo de plataforma
1x2 – 8 m

volume terraplenagens
6 950 m3 escavação
75 m3 aterro
soapro estudos e projectos
hydraulic eng.
transport inf.
electrical eng.